40.5T Rail-Mounted Gantry Crane Installation for Port Logistics Efficiency

DATE : July9, 2025
Share :

gantry crane1.jpg

Key SpecificationProject Background

Client: Coastal container terminal operator in South Africa.

Core challenges:

The cost of manually handling containers ranging from 20 to 45 feet in length is extremely high, with an average handling time of 22 minutes each time. Currently, our existing cranes will overwork or have inaccurate positioning when handling special loads. Therefore, the growing demand (a 35% year-on-year increase) exceeds the production capacity of our existing cranes.

Solution Objective:

Install a 40.5T Rail-Mounted Gantry Crane (RMG) with ISO-container-specific features:

Key SpecificationValuePurpose
Lifting Capacity40.5 tonsHandles 20ft/40ft/45ft containers + tanks
Span30 metersCovers 4 rail tracks + truck lanes
Lifting Height18.2 metersStacks containers 5-high safely
Lifting MechanismSpreader BeamAuto-locks ISO twistlocks in 8 sec
Power Supply380V/50Hz/3PhStandard industrial supply
Operating Temperature-20°C to +40°Cuitable for coastal climates

Sinoko Crane Features: Precision & Power for Containers

A. Intelligent Container Handling

Spreaders:

Hydraulic telescopic beam adjusts to 20ft/40ft/45ft containers instantly.

Sensors detect container weight distribution (stops overload).

Anti-Sway Technology:

GPS-guided trolley reduces swing by 90% (critical in windy ports).

B. Rugged All-Weather Design

High-Torque Hoists:

3x 15kW motors lift 25 m/min at 100% capacity (-20°C cold start capability).

Corrosion Defense:

Sandblasted steel + epoxy coating resists saltwater spray (IP66 rating).

C. Operator-Centric Control

Ergonomic Cabin:

Air-conditioned, 360° visibility, shock-absorbing seats.

Dual Control Modes:

Cabin + remote control (range: 150m).

gantry crane2.jpg

Implementation: From Rails to Reality

Starting from receiving the customer's inquiry, Sinokocrane immediately designs a solution for the customer. It also dispatches engineers to the customer's project site for on-site coordination. After the installation is completed, it conducts training for the customer's employees on the use of the crane.

Phase 1: Infrastructure (4 Weeks)

Laid 200m dual rails (P43 steel) with laser-aligned flatness (±2mm tolerance).

Installed substation for uninterrupted power (backup generators on-site).

Phase 2: Crane Assembly & Testing (3 Weeks)

Key Tests:

120% Load Test: 48.6 tons lifted with ≤5mm deflection.

Wind Resilience: Stable at Beaufort Scale 6 (45 km/h winds).

Spreader Calibration: 20-cycle twistlock test (0 failures).

Operator Training:

Simulator-based modules for collision avoidance + emergency drills.

Project Outcomes

Sinokocrane always keeps in touch with the clients even after the project is completed, asking about their usage. This client has provided us with the following genuine feedback.

Operational Transformation:

MetricBeforeAfterImprovement
Transfer time/container22 min7 min68% faster
Daily throughput160 TEU400 TEU+150%
Accident rate7/yr0100% safer
Energy use/container9.8 kWh5.2 kWh47% savings

Strategic Benefits:

ROI: Achieved in 11 months via labor/fuel savings.

Space Efficiency: 30m span eliminated relocating containers between cranes.

Uptime: 98.6% (vs. industry 89%) with predictive maintenance sensors.

Expanding Applications

IndustryApplicationWhy It Fits
Intermodal Rail HubsTransfer between trains/trucks30m span covers multiple rail tracks
Heavy Cargo PortsHydraulic tanks, project cargo40.5T capacity + spreader stability
Warehouse IntegrationContainer stacking/storage18.2m height enables high-density storage
Wind Energy LogisticsTurbine component handlingSubzero cold-start capability (-20°C)

Sinokocranes gantry cranes are applicable to a wide range of industries. Should you encounter challenges in material lifting, please do not hesitate to contact us. We are professionals in this field!



Related Products

Gantry cranes come in different tonnage capacities, and different tonnages can be applied to different scenarios. Sinokocranes can customize cranes of various tonnages.

4 ton Gantry Crane

4 ton Gantry Crane

4 ton gantry crane is ideal for getting your lightweight lifting jobs done quickly and safely, You can get high quality gantry cranes from our group with factory price and fast delivery.

Learn More                            Get a Quote
50t Gantry Crane

50t Gantry Crane

50t Rail Mounted Double Girder Container Gantry Cranes are mainly used for container handling, handling and stacking of container railway transfer yards and large container storage yards. Get a free quote.

Learn More                            Get a Quote
150 ton Gantry Crane

150 ton Gantry Crane

150 Ton Gantry Crane is widely used in open warehouses, material stocks area, cement plant, granite industry, and construction industry, engineering industry, railway station to lifting and load, unloading goods. Contact us today at www.sinokocrane.com

Learn More                            Get a Quote